Abouhamad, M and Zayed, T (2019) Risk-Based Asset Management Framework for Subway Systems. Journal of Construction Engineering and Management, 145(11).

Ahn, C R, Lee, S, Sun, C, Jebelli, H, Yang, K and Choi, B (2019) Wearable Sensing Technology Applications in Construction Safety and Health. Journal of Construction Engineering and Management, 145(11).

Alruwaythi, O and Goodrum, P (2019) A Difference in Perspective: Impact of Different Formats of Engineering Information and Spatial Cognition on Craft-Worker Eye-Gaze Patterns. Journal of Construction Engineering and Management, 145(11).

Cheng, M, Chang, Y and Korir, D (2019) Novel Approach to Estimating Schedule to Completion in Construction Projects Using Sequence and Nonsequence Learning. Journal of Construction Engineering and Management, 145(11).

Demirel, H &, Volker, L, Leendertse, W and Hertogh, M (2019) Dealing with Contract Variations in PPPs: Social Mechanisms and Contract Management in Infrastructure Projects. Journal of Construction Engineering and Management, 145(11).

Esmaeeli, A N and Heravi, G (2019) Real Options Approach versus Conventional Approaches to Valuing Highway Projects under Uncertainty. Journal of Construction Engineering and Management, 145(11).

Feng, Y and Trinh, M T (2019) Developing Resilient Safety Culture for Construction Projects. Journal of Construction Engineering and Management, 145(11).

Franco-Duran, D M and Garza, J M d l (2019) Review of Resource-Constrained Scheduling Algorithms. Journal of Construction Engineering and Management, 145(11).

  • Type: Journal Article
  • Keywords: Critical path; Delay analysis; Phantom float; Resource-constrained schedules; Resource relationships;
  • ISBN/ISSN: 0733-9364
  • URL: https://doi.org/10.1061/(ASCE)CO.1943-7862.0001698
  • Abstract:
    On a regular basis, project managers concentrate their efforts on critical and near-critical activities. However, the concepts of total float and critical path lose their significance after applying resource-constrained scheduling (RCS) techniques. RCS techniques mitigate the resource supply-demand problem but break the critical path. As a result, several algorithms have been developed to identify a continuous critical path in resource-constrained schedules. This study reviews and evaluates the performance of eight RCS-related algorithms with the purpose of identifying the shortcomings that must be addressed so they can be applied for delay analysis. The review shows that a systematic procedure is needed to (1) incorporate and handle dynamic resource links when the schedule is updated, and (2) select a potential resource links configuration. Addressing these limitations will make the algorithms more practical for real construction and engineering projects and will allow a more realistic delay analysis since schedules will reflect the real conditions of the project (resource loaded). This study (1) discusses potential solutions to the shortcomings of the existing algorithms, (2) provides recommendations on the methods that can be used by industry professionals, and (3) proposes a system to facilitate the selection of an algorithm based on the common features (heuristic), constraints (removal of logic links), and project characteristics (resources and calendars).

Hamzeh, F R, El Samad, G and Emdanat, S (2019) Advanced Metrics for Construction Planning. Journal of Construction Engineering and Management, 145(11).

Jang, Y, Jeong, I, Cho, Y K and Ahn, Y (2019) Predicting Business Failure of Construction Contractors Using Long Short-Term Memory Recurrent Neural Network. Journal of Construction Engineering and Management, 145(11).

Khalafallah, A and Shalaby, Y (2019) Change Orders: Automating Comparative Data Analysis and Controlling Impacts in Public Projects. Journal of Construction Engineering and Management, 145(11).

Li, K and Cheung, S O (2019) Unveiling Cognitive Biases in Construction Project Dispute Resolution through the Lenses of Third-Party Neutrals. Journal of Construction Engineering and Management, 145(11).

Prakash, A and Phadtare, M (2019) Exploration of Logic in Project Marketing Using Interpretive Structural Modeling. Journal of Construction Engineering and Management, 145(11).